A Research and Development team is creating a project plan for developing a new product. Determine the estimated duration of the project.
?
Activity
Immediate Predecessor
Activities
Optimistic
Time (to)
Most Likely Time (tm)
Pessimistic
Time (tp)
A
—
10
12
15
B
6
14
C
20
D
9
18
E
5
8
F
C, E
13
G
16
H
B, D
21
24
I
J
F, G, H